The weather finally cooperated at our Shuck Road Culvert project. The aluminum box culvert was able to be set this week.
It’s been a busy week and a half at the project site. The contractor, Rylind Construction, placed shale fill on both advance approaches beyond the bridge MSE wall limits. This fill is subbase for the future approach roadway. They placed geogrid and stone backfill behind the MSE walls, removed the Jersey Barrier from the stream, placed rip-rap at all 4 corners of the bridge and restored the stream channel under the bridge.
If you’re ready to start a new project, or to request more information, call us.